Cognos 10 Administrator - Scheduling a Report:
A report can be scheduled based on Daily, Monthly, Weekly, Yearly timeframe or can be event based.
We can also specify the formats in which the reports are to be scheduled.
Also, we can send these reports through email / save them / Print them.
       

Steps:
1- Click the Scheduling option available in front of every Report.
2- Specify the run criteria / output format / save method  
3- You can monitor these reports from the Administration screen.

Lets see....    

4- You can see the report which are currently running in the Current Activities
5- Future schedules in the upcoming activities.

6- Lets see the output of the report.